Quick answer
A lift's emergency phone must let a trapped passenger speak to someone who can get them out, and it must keep working in a power cut. The analogue line that has been doing that job stops working on 31 January 2027. Because the replacement has to survive a building-wide power failure, it usually cannot be your office broadband - the standard answer is a self-contained mobile (GSM) lift line unit with its own battery backup. This is work for your lift maintenance company, it needs a signal check inside the shaft, and lead times are among the longest in the whole switch-off. Treat it as the first item in your plan, not the last.
I put lifts and alarms at the top of every switch-off plan we write, and lifts are the more clear-cut of the two. With an alarm there is a genuine conversation to have about grades and risk appetite. With a lift there is not much of a conversation: somebody is stuck in a metal box and needs to talk to a human, and that has to work when the power is off. Everything about the replacement follows from that single requirement. If you also need the building's phone lines and connectivity sorted around your lift engineer's schedule, get a no-obligation quote - but book the lift company first.
Why the lift line is different from every other line
Every other analogue line in your building can, in principle, be replaced with something that runs over your internet connection and accepts that a power cut means no service for a while. The phones go quiet, someone gets the mobiles out, business carries on.
A lift cannot work that way, for an obvious reason: the most likely moment for someone to be trapped in a lift is a power cut. A solution that fails in exactly the scenario that creates the emergency is not a solution. That is why lift emergency communications have always been treated separately, why the old analogue line suited them so well - it carried its own power from the exchange - and why replacing it needs more thought than replacing a desk phone.
The second difference is who is responsible. If your phones are down for an afternoon, that is an inconvenience. If a lift's emergency phone is not working and somebody is trapped, that is a health and safety matter with your name on it.
What is actually required
Passenger lifts are required to provide a means of two-way voice communication from inside the car to a rescue service that can respond, and that communication has to remain available when normal power is not - which is why lift emergency units carry their own batteries. The specific standards and maintenance regime are your lift company's territory, and they will specify what your installation needs. Rather than paraphrase standards, ask them to tell you in writing:
- what the emergency communication path is today and what it depends on;
- what the compliant replacement is for your specific lift;
- how long it will continue to operate on battery after a mains failure;
- how the unit reports its own faults, so a dead line does not go unnoticed;
- who answers the call at the other end, and whether that arrangement changes.
That last point catches people out. Some lift phones dial a monitoring centre; others dial a mobile or an office number that may not be answered at 7pm on a Sunday. The switch-off is a good moment to fix that if it is wrong, because you are paying for an engineer visit anyway.
Why you cannot just put it on the office broadband
Three reasons, and they compound:
- Power. Your router, switches and any adapter all stop in a mains failure. A lift emergency phone must not. Even with a UPS, you are betting a trapped passenger's ability to call for help on a battery somebody remembered to test.
- Dependency on your IT. Broadband faults, router reboots, firewall changes, an IT contractor rewiring a comms room - all normal events that would silently take a safety-critical phone out of service.
- Silent failure. A lift phone that has stopped working looks exactly like a lift phone that is working. Purpose-built units supervise themselves and report faults; an improvised setup does not.
The same reasoning explains why an analogue telephone adapter is not the answer here either. It is a reasonable way to keep an ordinary handset or an undemanding device going, as we cover in keeping your existing phone system, but it inherits every one of the three problems above. Do not let anyone solve your lift line with an adapter and a shrug.
What replaces the analogue lift line
| Option | How it works | When it fits | Watch out for |
|---|---|---|---|
| Mobile (GSM) lift line unit | Self-contained unit with a SIM and internal battery, fitted in the car or machine room | The default for the large majority of installations | Mobile signal in the shaft; needs an aerial in many buildings |
| IP with dedicated resilience | Voice over a connection with UPS-backed power and a mobile fallback | Occasionally used in large managed buildings with proper resilience already | Only as good as the power and network design behind it; more to go wrong |
| Multi-network mobile SIM | As above, but the SIM can use more than one mobile network | Sites with marginal coverage from a single network | Slightly higher cost, usually worth it where signal is borderline |
For most UK businesses with one or two lifts, it is the first row. The unit is designed for the job: battery-backed, self-testing, and independent of everything else in the building.
The catch nobody plans for: signal
Lift motor rooms are often in basements. Lift shafts are concrete and steel. Mobile signal in both is frequently poor and occasionally nonexistent - and a mobile-based lift phone with no signal is not a solution, it is a fault waiting to be discovered at the worst possible time.
So insist on a signal survey at the actual location of the unit, not a coverage map for the postcode. Where signal is marginal the usual fixes are an external aerial run to a better position, a multi-network SIM, or occasionally repositioning the unit. All of these are routine - but they add cost and, more importantly, they add time, because the survey has to happen before the order.
This is the single best argument for starting early. A survey that finds a problem in September gives you months to solve it. The same survey in December does not.
Who does what, and how long it takes
| Task | Who | Typical lead time (as a guide, August 2026) |
|---|---|---|
| Identify the current emergency communication path | Lift maintenance company | Days |
| Signal survey at the unit's location | Lift company or their subcontractor | Days to weeks - do this first |
| Quote and specify | Lift company | Days to weeks |
| Fit, commission and test the new unit | Lift company | 4-12 weeks from order, driven by engineer availability |
| Aerial installation, if needed | Lift company or contractor | Adds time; may need access equipment |
| Confirm who answers and update records | You, with the lift company | Same visit |
| Cease the old lift line | Telecoms provider | Only once the new unit is proven |
The pattern is the same as with alarm signalling: the constraint is skilled engineers' diaries, not equipment availability. Both trades are working through a national backlog with a fixed deadline at the end of it, and both get harder to book every month. Our switch-off deadline guide sets out how that shapes the rest of the timeline.
What it costs
Expect this to be the largest single one-off item in a typical business's switch-off, and budget for it accordingly. The shape of the cost is a one-off charge per lift covering the unit, installation and commissioning, plus an ongoing monthly charge for the SIM connectivity and any monitoring or answering arrangement. An aerial installation, or access equipment to fit one, is extra.
We are not going to publish a specific figure, because the range is genuinely wide - a straightforward unit in a machine room with good signal and a difficult installation in a basement shaft needing an aerial run are different jobs. Get it quoted per lift, with equipment, labour, aerial work and ongoing charges itemised separately, and check whether your lift maintenance contract renewal is being folded into the same conversation. Our switch-off cost guide puts it in context alongside everything else.
If you have several lifts or several sites
Two things change. The per-lift cost usually improves when you do them together, so get one quote covering the estate rather than site by site. And sequencing becomes the main risk: you want one schedule covering the surveys, the installs and the line ceases across every building, with somebody owning it - the discipline we describe in migrating multi-site and multi-line businesses. Lifts are the item most likely to be forgotten at the site nobody visits often.
Check the answering arrangement per building too. A trapped passenger in an unstaffed unit at 9pm needs the call to reach someone who can actually attend, not a reception desk that closed at five.
Six questions to ask your lift maintenance company
- What does our lift's emergency phone use today, and is it on an analogue line?
- What are you proposing to replace it with, and how long does it run on battery after a mains failure?
- Have you surveyed the mobile signal at the unit's actual location, and do we need an aerial?
- How does the unit report its own faults, and who is notified?
- Who answers the emergency call once this changes, and is that arrangement appropriate out of hours?
- What is the one-off cost per lift, the ongoing monthly cost, and the earliest engineer date you can commit to?
Ask question three explicitly. It is the one most often skipped, and the one that causes the delays.
The bottom line
The lift emergency line is the least negotiable item in the switch-off. It has to work when the power is off, which rules out putting it on your office broadband and rules out an adapter. The standard answer is a battery-backed mobile lift line unit fitted by your lift company, and the thing that decides whether it goes smoothly is a signal survey done early enough to fix a bad result. It is also probably your biggest one-off cost, so get it quoted properly.
Ring your lift maintenance company this week and ask the six questions above. If you want us to handle the building's lines and connectivity around their schedule - and to make sure the old lift line is only ceased once the new unit is proven - get a no-obligation quote or call 0333 006 9399.
Getting unknown calls on a business line? Our free UK phone number checker shows which network or provider Ofcom allocated any number to, and whether the range is in service — no sign-up.
Frequently asked questions
Does the PSTN switch-off affect lift emergency phones?
Yes, and it is one of the highest-priority items. Lift emergency phones have traditionally used an analogue line, and that line stops working after 31 January 2027. Because a lift phone must also work during a power cut, it needs a purpose-built replacement rather than a standard digital phone line.
Can a lift emergency phone run over broadband?
Generally no, and you should be sceptical of anyone who suggests it. Your router and any adapter stop working in a mains failure, which is exactly when someone is most likely to be trapped. A lift line also should not depend on the building's IT, and an improvised setup fails silently. Purpose-built units carry their own battery and report their own faults.
What replaces an analogue lift phone line?
For most installations, a self-contained mobile (GSM) lift line unit with an internal battery, fitted in the car or machine room by your lift maintenance company. Where signal is marginal, a multi-network SIM or an external aerial is used. IP-based options exist in large managed buildings that already have proper power and network resilience.
Who is responsible for upgrading the lift emergency line?
Your lift maintenance company. It is their equipment, their commissioning and their compliance paperwork. No telecoms provider's migration includes your lift, so if you only tell your phone provider you are migrating, this job will not happen.
What if there is no mobile signal in the lift shaft?
This is common in basements and concrete shafts, and it is why a signal survey at the unit's exact location must happen before anything is ordered. The usual remedies are an external aerial run to a better position, a multi-network SIM, or repositioning the unit. All are routine, but they add cost and time - which is why surveying early matters.
How much does a lift line replacement cost?
It is typically the largest single one-off item in a business's switch-off project, made up of a per-lift charge for the unit, installation and commissioning, plus an ongoing monthly charge for the SIM and any answering arrangement. Aerial work is extra. Get it itemised per lift rather than as a single figure, and check whether a maintenance contract renewal is being bundled in.
When should I book the work?
Now. Lead times of four to twelve weeks from order are normal and lengthening, the survey has to happen before the order, and any aerial work adds more time again. Together with alarm signalling, this is the item that determines whether the rest of your migration is comfortable or rushed.